Currently, NIMIT Langsuan development has reached Level 54 with approximately 50% completion on internal architectural work while MEPF system (mechanical, electrical, plumbing and fire) is 30% complete and façade installation is 25% complete.
Last Remaining Units Available
Call +66 80 071 2000 or
Email [email protected]   
Construction Update

Construction of WINDSHELL Naradhiwas has reached Roof Deck level. Works on the show-suites have included trees placement throughout the balconies. The MEP duct-bank work is fully complete, and the retention tank work has started. WINDSHELL Naradhiwas’ construction is expected to topped-out by the end of this month.
For more information,
Call +662 234 1414 or
Email 
[email protected]
MahaSamutr CSR Activity

MahaSamutr team and MahaSamutr Country Club Members recently donated unused clothes, sport equipments, stationeries and other necessary items for underprivileged children. The activity was held at Border Patrol Police School in Baan Pong Luek, Khang Krajan, Petchaburi, on February 16, 2019.

For membership or luxury villas information, 
Call +66 32 907 900 or
Email [email protected] 
Thank you for your interest, and your decision to purchase or invest with us.  
If you have any questions or comments about your property or would like
to find out more about PACE, please do not hesitate to contact our team. 


Contact Us:
PACE Corporate: Tel. +662 118 9599   Email: [email protected]
WINDSHELL Naradhiwas: Tel. +662 234 1414  Email: [email protected]
NIMIT Langsuan: Tel. +66 80 071 2000   Email: [email protected]
MahaSamutr: Tel.  +66 32 907 900   Email: [email protected]   
Investor Relations: Tel. +662 118 9599   Email: [email protected]

 

Unsubscribe from this list
 
Prepared by PACE Corporate Communications 
Copyright © | 2019 | PACE Development Corporation Plc. |  All rights reserved.
ภาษาไทย คลิกที่นี่